 "id": "rd2f8fecf174",
 "found": true,
 "parent_id": "r368908849d6",
 "created_at": "2026-08-31 21:18:36.758966+00:00",
 "rows": [
  {
   "project": "PORTS Technology Campus",
   "source_mentions": 154,
   "locality": "Pike County",
   "state": "Ohio",
   "builder": "SB Energy",
   "customer": "OpenAI",
   "capacity_gw": 8.0,
   "capacity_basis": "ultimate planned",
   "status": "planned",
   "target_date": "2028",
   "source_url": "https://datacenterdynamics.com/en/news?company=openai&term=the-data-center-construction-channel",
   "latest_source_date": "2026-08-27T00:00:00"
  },
  {
   "project": "Abilene",
   "source_mentions": 144,
   "locality": "Abilene",
   "state": "Texas",
   "builder": "Crusoe",
   "customer": "OpenAI",
   "capacity_gw": 1.2,
   "capacity_basis": "ultimate planned",
   "status": "under construction",
   "target_date": "mid-2026",
   "source_url": "https://x.com/CatchUpFeed/status/2093098314761654616",
   "latest_source_date": "2026-08-27T22:08:20"
  },
  {
   "project": "Hyperion",
   "source_mentions": 139,
   "locality": "Richland Parish",
   "state": "Louisiana",
   "builder": "Meta",
   "customer": "Meta",
   "capacity_gw": 5.0,
   "capacity_basis": "ultimate planned",
   "status": "under construction",
   "target_date": "2030",
   "source_url": "https://cryptobriefing.com/meta-robots-data-center-maintenance",
   "latest_source_date": "2026-08-28T16:05:35"
  },
  {
   "project": "Paducah",
   "source_mentions": 122,
   "locality": "Paducah",
   "state": "Kentucky",
   "builder": "Brookfield",
   "customer": null,
   "capacity_gw": 1.8,
   "capacity_basis": "new AI data center campus",
   "status": "planned",
   "target_date": "2031",
   "source_url": "https://activistpost.com/trump-calls-for-rapid-expansion-of-ai-data-centers-including-on-federal-lands",
   "latest_source_date": "2026-08-25T16:00:00"
  },
  {
   "project": "Colossus",
   "source_mentions": 99,
   "locality": "Memphis",
   "state": "Tennessee",
   "builder": "xAI",
   "customer": "xAI",
   "capacity_gw": 1.0,
   "capacity_basis": "expected to require more than a gigawatt of electricity",
   "status": "active construction still on site",
   "target_date": "2026",
   "source_url": "https://sourcefeed.dev/a/xai-turned-unpermitted-gas-into-a-compute-moat",
   "latest_source_date": "2026-08-07T03:10:59"
  },
  {
   "project": "AWS Project Rainier",
   "source_mentions": 85,
   "locality": "New Carlisle",
   "state": "Indiana",
   "builder": "Amazon Web Services",
   "customer": "Anthropic",
   "capacity_gw": 2.2,
   "capacity_basis": "ultimate planned",
   "status": "operational",
   "target_date": "2024",
   "source_url": "https://en.wikipedia.org/wiki/AI_factory",
   "latest_source_date": "2026-08-26T14:30:55"
  },
  {
   "project": "MACROHARDRR",
   "source_mentions": 71,
   "locality": "Southaven",
   "state": "Mississippi",
   "builder": "xAI",
   "customer": "xAI",
   "capacity_gw": 2.0,
   "capacity_basis": "plans to bring xAI's training compute up to 2 gigawatts of electricity",
   "status": "under construction",
   "target_date": "February 2026",
   "source_url": "https://legalclarity.org/elon-musk-in-memphis-xai-pollution-permits-and-lawsuits",
   "latest_source_date": "2026-06-28T11:52:12"
  },
  {
   "project": "Meta Project Prometheus",
   "source_mentions": 68,
   "locality": "New Albany",
   "state": "Ohio",
   "builder": "Meta",
   "customer": "Meta",
   "capacity_gw": 1.0,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "planned",
   "target_date": "2026",
   "source_url": "https://finance.yahoo.com/technology/ai/articles/openai-build-worlds-biggest-ai-013035509.html",
   "latest_source_date": "2026-08-25T01:30:35"
  },
  {
   "project": "Muskie Data Campus",
   "source_mentions": 55,
   "locality": "Eastern Kentucky",
   "state": "Kentucky",
   "builder": "TeraWulf Inc.",
   "customer": null,
   "capacity_gw": 1.0,
   "capacity_basis": "ultimate planned",
   "status": "acquired",
   "target_date": "second half of 2030",
   "source_url": "https://kentucky.com/news/state/kentucky/article316830997.html",
   "latest_source_date": "2026-08-11T09:00:00"
  },
  {
   "project": "Childress",
   "source_mentions": 46,
   "locality": "Childress",
   "state": "Texas",
   "builder": "Crusoe and Lancium",
   "customer": "a leading hyperscale technology company",
   "capacity_gw": 1.0,
   "capacity_basis": "announced",
   "status": "announced",
   "target_date": "Q3 2026",
   "source_url": "https://datacenterdynamics.com/en/news?company=meta&term=the-data-center-construction-channel",
   "latest_source_date": "2026-08-27T00:00:00"
  },
  {
   "project": "El Paso",
   "source_mentions": 37,
   "locality": "El Paso",
   "state": "Texas",
   "builder": "Meta",
   "customer": "Meta",
   "capacity_gw": 1.0,
   "capacity_basis": "ultimate planned",
   "status": "Planned",
   "target_date": "2028",
   "source_url": "https://datacenterdynamics.com/en/news?company=meta&term=the-data-center-construction-channel",
   "latest_source_date": "2026-08-27T00:00:00"
  },
  {
   "project": "Frontier",
   "source_mentions": 32,
   "locality": "Shackelford County",
   "state": "Texas",
   "builder": "Vantage Data Centers",
   "customer": "Oracle",
   "capacity_gw": 1.4,
   "capacity_basis": "planned",
   "status": "Announced",
   "target_date": "second half of 2026",
   "source_url": "https://4pillarfunding.com/insights/texas-data-center-capital-outlook",
   "latest_source_date": "2026-08-12T00:00:00"
  },
  {
   "project": "Project Matador",
   "source_mentions": 30,
   "locality": "Amarillo",
   "state": "Texas",
   "builder": "Fermi America",
   "customer": "TensorWave",
   "capacity_gw": 17.0,
   "capacity_basis": "ultimate planned",
   "status": "proposed",
   "target_date": "2026",
   "source_url": "https://datacenterdynamics.com/en/news/fermi-secures-natural-gas-pipeline-connection-for-up-to-11gw-data-center-project-in-amarillo-texas",
   "latest_source_date": "2026-08-27T00:00:00"
  },
  {
   "project": "GW Ranch",
   "source_mentions": 29,
   "locality": "Pecos County",
   "state": "Texas",
   "builder": "Pacifico Energy",
   "customer": "Amazon",
   "capacity_gw": 7.65,
   "capacity_basis": "ultimate planned",
   "status": "planned",
   "target_date": "Q1 2027",
   "source_url": "https://reactortech.substack.com/p/amazons-ai-campus-could-become-americas?action=share",
   "latest_source_date": "2026-08-19T05:28:27"
  },
  {
   "project": "Fairwater",
   "source_mentions": 27,
   "locality": "Mount Pleasant",
   "state": "Wisconsin",
   "builder": "Microsoft",
   "customer": "Microsoft",
   "capacity_gw": 3.3,
   "capacity_basis": "projected IT power",
   "status": "Under Construction",
   "target_date": "2024",
   "source_url": "https://irecruit.co/insights/hyperscale-data-center-news-tracking-mega-builds",
   "latest_source_date": "2026-08-16T05:53:53"
  },
  {
   "project": "Project Jupiter",
   "source_mentions": 19,
   "locality": "Santa Teresa",
   "state": "New Mexico",
   "builder": "STACK Infrastructure",
   "customer": "OpenAI",
   "capacity_gw": 1.0,
   "capacity_basis": "Projected capacity",
   "status": "Planned",
   "target_date": "Q4 2028",
   "source_url": "https://siliconreport.com/biggest-ai-data-centers-us-ranked-power-8becb4fb",
   "latest_source_date": "2026-07-03T07:52:38"
  },
  {
   "project": "Lighthouse",
   "source_mentions": 16,
   "locality": "Port Washington",
   "state": "Wisconsin",
   "builder": "Vantage Data Centers",
   "customer": "OpenAI",
   "capacity_gw": 1.0,
   "capacity_basis": "Projected capacity",
   "status": "planned",
   "target_date": "2028",
   "source_url": "https://theregister.com/ai-and-ml/2026/07/21/oracle-faces-100m-annual-bill-to-back-wisconsin-datacenter-power-promises/5275728",
   "latest_source_date": "2026-07-21T16:45:35"
  },
  {
   "project": "Stargate Michigan",
   "source_mentions": 15,
   "locality": "Saline Township",
   "state": "Michigan",
   "builder": "Related Digital",
   "customer": "OpenAI",
   "capacity_gw": 1.4,
   "capacity_basis": "Projected capacity",
   "status": "Under construction",
   "target_date": "Q4 2028",
   "source_url": "https://datacenterdynamics.com/en/news/blue-owl-opts-not-to-fund-oracles-10bn-michigan-data-center",
   "latest_source_date": "2026-08-19T00:00:00"
  },
  {
   "project": "Beacon Point",
   "source_mentions": 15,
   "locality": "Nueces County",
   "state": "Texas",
   "builder": "Hut 8",
   "customer": "unnamed \"high-investment-grade company\"",
   "capacity_gw": 1.0,
   "capacity_basis": "utility capacity",
   "status": "fully commercialized",
   "target_date": "2027",
   "source_url": "https://axis-intelligence.com/ai-data-center-tracker",
   "latest_source_date": "2026-08-13T09:05:23"
  },
  {
   "project": "Lebanon",
   "source_mentions": 15,
   "locality": "Lebanon",
   "state": "Indiana",
   "builder": "Meta",
   "customer": "Meta",
   "capacity_gw": 1.0,
   "capacity_basis": "once operational",
   "status": "Announced",
   "target_date": "2026",
   "source_url": "https://irecruit.co/insights/hyperscale-data-center-news-tracking-mega-builds",
   "latest_source_date": "2026-08-16T05:53:53"
  },
  {
   "project": "Project Kilby",
   "source_mentions": 9,
   "locality": "Reeves County",
   "state": "Texas",
   "builder": "Chevron",
   "customer": "Microsoft",
   "capacity_gw": 2.67,
   "capacity_basis": "take-or-pay power purchase agreement",
   "status": "Announced",
   "target_date": "2028",
   "source_url": "https://edgen.tech/news/post/chevrons-20-year-microsoft-power-deal-diversifies-beyond-oil",
   "latest_source_date": "2026-08-29T15:54:13"
  },
  {
   "project": "Monach Compute Campus",
   "source_mentions": 9,
   "locality": "Mason County",
   "state": "West Virginia",
   "builder": "Nscale",
   "customer": "Microsoft",
   "capacity_gw": 8.0,
   "capacity_basis": "ultimate planned",
   "status": "planned",
   "target_date": "2027",
   "source_url": "https://datacenterdynamics.com/en/news/nscale-in-talks-to-acquire-8gw-monarch-compute-campus-in-west-virginia-report",
   "latest_source_date": "2026-08-05T00:00:00"
  },
  {
   "project": "Google Nebraska Data Center",
   "source_mentions": 9,
   "locality": "Nebraska",
   "state": "Nebraska",
   "builder": "Google",
   "customer": "Google",
   "capacity_gw": 2.7,
   "capacity_basis": "data center requirement",
   "status": "Planned",
   "target_date": "2029",
   "source_url": "https://aidatacenterindex.com/compare/google-vs-amazon",
   "latest_source_date": "2026-04-04T00:45:35"
  },
  {
   "project": "Meta\u2013Oklo Advanced Nuclear AI Campus",
   "source_mentions": 8,
   "locality": "Ohio",
   "state": "Ohio",
   "builder": "Meta",
   "customer": "Meta",
   "capacity_gw": 1.2,
   "capacity_basis": "clean, baseload power",
   "status": "Announced",
   "target_date": "2030",
   "source_url": "https://aidatacenterindex.com/compare/bytedance-vs-meta",
   "latest_source_date": "2026-04-04T00:45:35"
  },
  {
   "project": "AWS \u2014 Mississippi AI Data Center",
   "source_mentions": 8,
   "locality": "Madison County",
   "state": "Mississippi",
   "builder": "Amazon Web Services",
   "customer": "Amazon Web Services",
   "capacity_gw": 1.3,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "Under Construction",
   "target_date": "2024",
   "source_url": "https://aidatacenterindex.com/compare/google-vs-amazon",
   "latest_source_date": "2026-04-04T00:45:35"
  },
  {
   "project": "AWS AI Innovation Campuses (Salem and Falls Townships, PA)",
   "source_mentions": 8,
   "locality": "Salem and Falls Townships",
   "state": "Pennsylvania",
   "builder": "Amazon Web Services",
   "customer": null,
   "capacity_gw": 1.8,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "under construction",
   "target_date": "2025",
   "source_url": "https://aidatacenterindex.com/compare/google-vs-amazon",
   "latest_source_date": "2026-04-04T00:45:35"
  },
  {
   "project": "Port Washington",
   "source_mentions": 8,
   "locality": "Port Washington",
   "state": "Wisconsin",
   "builder": "Microsoft and OpenAI",
   "customer": "OpenAI",
   "capacity_gw": 1.3,
   "capacity_basis": "planned campus capacity",
   "status": "Planned",
   "target_date": "end of 2027",
   "source_url": "https://mgrid.org/entity/openai",
   "latest_source_date": "2026-08-17T13:00:00"
  },
  {
   "project": "AWS \u2014 Richmond County AI Innovation Campus",
   "source_mentions": 7,
   "locality": "Richmond County",
   "state": "North Carolina",
   "builder": "Amazon Web Services",
   "customer": "Amazon Web Services",
   "capacity_gw": 1.0,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "Under Construction",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Milam County",
   "source_mentions": 7,
   "locality": "Milam County",
   "state": "Texas",
   "builder": "SB Energy",
   "customer": "OpenAI",
   "capacity_gw": 1.2,
   "capacity_basis": "announced load",
   "status": "building",
   "target_date": "October 2026",
   "source_url": "https://4pillarfunding.com/insights/texas-data-center-capital-outlook",
   "latest_source_date": "2026-08-12T00:00:00"
  },
  {
   "project": "HyperGrid",
   "source_mentions": 7,
   "locality": "Amarillo",
   "state": "Texas",
   "builder": "Fermi America",
   "customer": null,
   "capacity_gw": 11.0,
   "capacity_basis": "ultimate planned",
   "status": "planned",
   "target_date": "2032",
   "source_url": "https://morningoverview.com/a-planned-texas-megacomplex-would-draw-11-gigawatts-from-nuclear-gas-solar-and-wind",
   "latest_source_date": "2026-08-25T13:05:00"
  },
  {
   "project": "Digital Realty \u2014 Project Bunkhouse",
   "source_mentions": 7,
   "locality": "Bartow County",
   "state": "Georgia",
   "builder": "Digital Realty",
   "customer": "Cloud hyp.",
   "capacity_gw": 1.83,
   "capacity_basis": "planned total capacity",
   "status": "Planned",
   "target_date": null,
   "source_url": "https://michaelbommarito.com/wiki/datacenters/projects/mega-projects",
   "latest_source_date": "2025-10-16T00:00:00"
  },
  {
   "project": "Microsoft Pecos Campus",
   "source_mentions": 7,
   "locality": "Pecos",
   "state": "Texas",
   "builder": "Microsoft",
   "customer": "Microsoft",
   "capacity_gw": 2.0,
   "capacity_basis": "ultimate planned",
   "status": "announced",
   "target_date": "early 2027",
   "source_url": "http://dlvr.it/TV6RJr",
   "latest_source_date": "2026-08-27T00:00:00"
  },
  {
   "project": "Cheyenne Power Hub (Project Jade campus)",
   "source_mentions": 7,
   "locality": "Switchgrass Industrial Park, Laramie County",
   "state": "WY",
   "builder": "Tallgrass Energy",
   "customer": "Crusoe",
   "capacity_gw": 2.7,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": "Jan 2026",
   "source_url": "https://measuredai.substack.com/p/google-wyoming-data-centers",
   "latest_source_date": "2026-08-12T11:03:00"
  },
  {
   "project": "Homer City",
   "source_mentions": 7,
   "locality": "Homer City",
   "state": "Pennsylvania",
   "builder": "Homer City Redevelopment",
   "customer": "AI / HPC tenants (undisclosed)",
   "capacity_gw": 4.5,
   "capacity_basis": "ultimate planned",
   "status": "Under construction",
   "target_date": "2027",
   "source_url": "https://gridglasses.com/brief/35-gigawatts-of-gas-the-grid-never-sees-n4m7",
   "latest_source_date": "2026-06-17T13:05:06"
  },
  {
   "project": "Amazon Web Services \u2014 Northern Virginia Hyperscale Campus",
   "source_mentions": 7,
   "locality": "Northern Virginia",
   "state": "Virginia",
   "builder": "Amazon Web Services",
   "customer": "Amazon Web Services",
   "capacity_gw": 1.5,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "Operational",
   "target_date": "2006",
   "source_url": "https://aidatacenterindex.com/compare/google-vs-amazon",
   "latest_source_date": "2026-04-04T00:45:35"
  },
  {
   "project": "Google Fort Wayne",
   "source_mentions": 7,
   "locality": "Fort Wayne",
   "state": "Indiana",
   "builder": "Google",
   "customer": "Google",
   "capacity_gw": 1.2,
   "capacity_basis": "operational capacity",
   "status": "Operational",
   "target_date": "2025-12",
   "source_url": "https://aidatacenterindex.com/compare/google-vs-amazon",
   "latest_source_date": "2026-04-04T00:45:35"
  },
  {
   "project": "Advanced Energy and Intelligence Campus",
   "source_mentions": 6,
   "locality": "Amarillo",
   "state": "Texas",
   "builder": "Texas University System & Fermi America",
   "customer": null,
   "capacity_gw": 11.0,
   "capacity_basis": "ultimate planned",
   "status": "Geo-technical work started in June 2025; the first 1 GW by the end of 2026",
   "target_date": "by the end of 2026",
   "source_url": "https://europesays.com/ai/12722",
   "latest_source_date": "2026-04-22T17:20:10"
  },
  {
   "project": "AWS New Carlisle Campus",
   "source_mentions": 6,
   "locality": "New Carlisle",
   "state": "IN",
   "builder": "Amazon",
   "customer": "Anthropic",
   "capacity_gw": 2.25,
   "capacity_basis": "permit approved",
   "status": "permit approved",
   "target_date": "Jan 2026",
   "source_url": "https://gridglasses.com/brief/the-145-gigawatt-build-the-queues-never-see-8sti",
   "latest_source_date": "2026-07-01T13:31:56"
  },
  {
   "project": "Freebird",
   "source_mentions": 5,
   "locality": "Milam County",
   "state": "Texas",
   "builder": "SB Energy",
   "customer": "OpenAI",
   "capacity_gw": 1.2,
   "capacity_basis": "facility capacity",
   "status": "Phase one of Freebird had officially topped out.",
   "target_date": "15 October",
   "source_url": "https://datacenterdynamics.com/en/news/openai-stargates-milam-texas-freebird-data-center-to-span-548950-sq-ft-in-first-phase",
   "latest_source_date": "2026-08-11T00:00:00"
  },
  {
   "project": "Savannah River Site",
   "source_mentions": 5,
   "locality": "Savannah River Site",
   "state": "South Carolina",
   "builder": "Amentum",
   "customer": null,
   "capacity_gw": 1.0,
   "capacity_basis": "planned",
   "status": "exploring",
   "target_date": null,
   "source_url": "https://activistpost.com/trump-calls-for-rapid-expansion-of-ai-data-centers-including-on-federal-lands",
   "latest_source_date": "2026-08-25T16:00:00"
  },
  {
   "project": "Microsoft Azure Northern Virginia AI Data Centers",
   "source_mentions": 5,
   "locality": "Northern Virginia (Loudoun, Prince William counties)",
   "state": "Virginia",
   "builder": "Microsoft",
   "customer": "Microsoft",
   "capacity_gw": 1.0,
   "capacity_basis": "operational capacity",
   "status": "Operational",
   "target_date": "2020",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Meta\u2013Vistra Nuclear Uprate Agreement",
   "source_mentions": 5,
   "locality": "Perry",
   "state": "OH",
   "builder": "Meta",
   "customer": "Meta",
   "capacity_gw": 2.1,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Data City Texas",
   "source_mentions": 5,
   "locality": "Laredo",
   "state": "Texas",
   "builder": "Energy Abundance Development Corporation",
   "customer": null,
   "capacity_gw": 5.0,
   "capacity_basis": "ultimate planned",
   "status": "First 300 MW + 1 M sq ft launching in 2026; full build phased",
   "target_date": "2026",
   "source_url": "https://datacentercompass.com/guides/list-of-us-data-centers-under-construction",
   "latest_source_date": "2026-04-19T00:00:00"
  },
  {
   "project": "Fundamental Data Ridgeline microgrid",
   "source_mentions": 4,
   "locality": "Tucker County (Davis)",
   "state": "WV",
   "builder": "Fundamental Data",
   "customer": "Microsoft (reported)",
   "capacity_gw": 1.7,
   "capacity_basis": "permitted",
   "status": "Permit applied",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Shackelford County",
   "source_mentions": 4,
   "locality": "Shackelford County",
   "state": "Texas",
   "builder": "Vantage Data Centers",
   "customer": "OpenAI",
   "capacity_gw": 1.4,
   "capacity_basis": "seeded",
   "status": "First building delivery is targeted for late 2026",
   "target_date": "2028",
   "source_url": "https://siliconreport.com/every-stargate-data-center-site-mapped-54f088b3",
   "latest_source_date": "2026-07-03T07:52:40"
  },
  {
   "project": "Google Gemini Cluster",
   "source_mentions": 4,
   "locality": "Midwest (Iowa\u2013Nebraska cluster)",
   "state": "United States",
   "builder": "Google",
   "customer": "Google",
   "capacity_gw": 1.0,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "Operational",
   "target_date": "2024",
   "source_url": "https://aidatacenterindex.com/compare/google-vs-amazon",
   "latest_source_date": "2026-04-04T00:45:35"
  },
  {
   "project": "Galaxy Helios Campus",
   "source_mentions": 4,
   "locality": "West Texas",
   "state": "Texas",
   "builder": "Galaxy Digital",
   "customer": "CoreWeave",
   "capacity_gw": 1.6,
   "capacity_basis": "doubled",
   "status": "Development",
   "target_date": "2026-01",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Vistra's Comanche Peak Nuclear Data Center Campus",
   "source_mentions": 4,
   "locality": "Glen Rose",
   "state": "Texas",
   "builder": "Vistra Corp.",
   "customer": null,
   "capacity_gw": 1.2,
   "capacity_basis": "power purchase agreement",
   "status": "Planned",
   "target_date": "2027",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Lordstown (Stargate OH)",
   "source_mentions": 4,
   "locality": "Lordstown",
   "state": "Ohio",
   "builder": "SoftBank",
   "customer": "OpenAI",
   "capacity_gw": 1.5,
   "capacity_basis": "announced load",
   "status": "building",
   "target_date": "2026",
   "source_url": "https://powertracker.io/rankings",
   "latest_source_date": "2026-05-18T23:52:00"
  },
  {
   "project": "Meitner Energy Center (Google/Intersect co-located data center)",
   "source_mentions": 4,
   "locality": "Gray and Roberts Counties",
   "state": "TX",
   "builder": "Google / Intersect",
   "customer": "Google",
   "capacity_gw": 1.0,
   "capacity_basis": "announced",
   "status": "Under construction",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "OpenAI Stargate Data Center",
   "source_mentions": 4,
   "locality": "Abilene",
   "state": "Texas",
   "builder": "OpenAI",
   "customer": "OpenAI",
   "capacity_gw": 1.2,
   "capacity_basis": "campus",
   "status": "Operational",
   "target_date": "2024",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Horizon",
   "source_mentions": 4,
   "locality": "Fort Stockton",
   "state": "Texas",
   "builder": "Poolside",
   "customer": "CoreWeave",
   "capacity_gw": 2.0,
   "capacity_basis": "planned",
   "status": "developing",
   "target_date": null,
   "source_url": "https://mercation.com/news/amazon-gas-power-plant-ai-data-center-texas",
   "latest_source_date": "2026-08-09T12:00:00"
  },
  {
   "project": "AWS AI Innovation Campuses",
   "source_mentions": 4,
   "locality": "Salem and Falls Townships",
   "state": "Pennsylvania",
   "builder": "Amazon Web Services",
   "customer": "Amazon Web Services",
   "capacity_gw": 1.0,
   "capacity_basis": "under construction campus capacity",
   "status": "Under Construction",
   "target_date": "2025",
   "source_url": "https://datacentercompass.com/guides/list-of-us-data-centers-under-construction",
   "latest_source_date": "2026-04-19T00:00:00"
  },
  {
   "project": "West Texas data center private gas power plant",
   "source_mentions": 3,
   "locality": "New Braunfels",
   "state": "TX",
   "builder": null,
   "customer": null,
   "capacity_gw": 1.2,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Diablo Canyon AI Integration Project",
   "source_mentions": 3,
   "locality": "Western United States",
   "state": "United States",
   "builder": "Pacific Gas and Electric Company (PG&E)",
   "customer": "Atomic Canyon",
   "capacity_gw": 2.3,
   "capacity_basis": "operational capacity",
   "status": "Operational",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "OpenAI Stargate Data Center (Texas)",
   "source_mentions": 3,
   "locality": "Abilene",
   "state": "Texas",
   "builder": "OpenAI",
   "customer": null,
   "capacity_gw": 1.2,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "Operational",
   "target_date": "2024",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "CloudBurst Data Centers San Antonio/San Marcos Campus",
   "source_mentions": 3,
   "locality": "San Marcos",
   "state": "TX",
   "builder": "CloudBurst Data Centers, Inc.",
   "customer": null,
   "capacity_gw": 1.2,
   "capacity_basis": "announced",
   "status": "Under construction",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Project Camellia",
   "source_mentions": 3,
   "locality": "Effingham County",
   "state": "Georgia",
   "builder": "OpenAI",
   "customer": "OpenAI",
   "capacity_gw": 3.2,
   "capacity_basis": "self-developed campus",
   "status": "Planned",
   "target_date": "2032",
   "source_url": "https://racetoagi.org/analysis/the-ai-buildout-signed-15-year-leases-against-a-price-that-resets-every-quarter",
   "latest_source_date": "2026-08-10T05:17:27"
  },
  {
   "project": "Data Center Ridge / Project Oasis",
   "source_mentions": 3,
   "locality": "Wise County",
   "state": "VA",
   "builder": "Energy DELTA Lab",
   "customer": null,
   "capacity_gw": 1.0,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Joule High Performance Compute Data Center Campus",
   "source_mentions": 3,
   "locality": "Millard County",
   "state": "UT",
   "builder": "Joule Capital Partners",
   "customer": null,
   "capacity_gw": 1.5,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Chevron \"Engine No. 1\" power project",
   "source_mentions": 3,
   "locality": "West Texas",
   "state": "TX",
   "builder": "Chevron",
   "customer": "Microsoft (reported)",
   "capacity_gw": 2.5,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Tract Caldwell County Park",
   "source_mentions": 3,
   "locality": "Caldwell County",
   "state": "Texas",
   "builder": "Tract",
   "customer": null,
   "capacity_gw": 2.0,
   "capacity_basis": "ultimate planned",
   "status": "Land acquisition completed in May 2025; 360 MW first phase operational in 2028",
   "target_date": "2028",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "CloudBurst New Braunfels AI Data Center",
   "source_mentions": 3,
   "locality": "New Braunfels",
   "state": "TX",
   "builder": "CloudBurst Data Centers",
   "customer": "CloudBurst Data Centers",
   "capacity_gw": 1.2,
   "capacity_basis": "announced",
   "status": "Under construction",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "OpenAI Stargate Campus",
   "source_mentions": 3,
   "locality": "Abilene",
   "state": "Texas",
   "builder": "OpenAI, Oracle, SoftBank",
   "customer": "OpenAI",
   "capacity_gw": 4.5,
   "capacity_basis": "ultimate planned",
   "status": "Under construction; phased build over 4 years",
   "target_date": "end of 2026",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "AWS US Government AI Supercomputing Expansion",
   "source_mentions": 3,
   "locality": "Virginia / Oregon / Ohio",
   "state": "United States",
   "builder": "Amazon Web Services",
   "customer": null,
   "capacity_gw": 1.3,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "Announced",
   "target_date": "2026",
   "source_url": "https://aidatacenterindex.com/compare/google-vs-amazon",
   "latest_source_date": "2026-04-04T00:45:35"
  },
  {
   "project": "TerraSite-TX1",
   "source_mentions": 3,
   "locality": "Houston",
   "state": "Texas",
   "builder": "ECL",
   "customer": "Lambda",
   "capacity_gw": 1.0,
   "capacity_basis": "ultimate planned",
   "status": "seeking funding",
   "target_date": "this summer",
   "source_url": "https://datacenterdynamics.com/en/news/ecl-says-it-will-build-a-1gw-hydrogen-powered-ai-data-center-in-texas-with-lambda-as-its-first-tenant",
   "latest_source_date": "2026-08-05T00:00:00"
  },
  {
   "project": "Tract Data Center Campus",
   "source_mentions": 3,
   "locality": "New Braunfels",
   "state": "TX",
   "builder": "Tract",
   "customer": null,
   "capacity_gw": 1.2,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Delta Gigasite",
   "source_mentions": 2,
   "locality": "Millard County",
   "state": "Utah",
   "builder": "Fibernet MercuryDelta LLC, Creekstone Energy, BluSky AI",
   "customer": "Creekstone Energy",
   "capacity_gw": 4.0,
   "capacity_basis": "planned capacity",
   "status": "Planned",
   "target_date": null,
   "source_url": "https://michaelbommarito.com/wiki/datacenters/projects/mega-projects",
   "latest_source_date": "2025-10-16T00:00:00"
  },
  {
   "project": "Prince William Digital Gateway",
   "source_mentions": 2,
   "locality": "Prince William County",
   "state": "VA",
   "builder": "QTS Realty Trust / Compass Datacenters",
   "customer": null,
   "capacity_gw": 2.7,
   "capacity_basis": "announced capacity",
   "status": "Announced",
   "target_date": null,
   "source_url": "https://datacentercompass.com/guides/list-of-us-data-centers-under-construction",
   "latest_source_date": "2026-04-19T00:00:00"
  },
  {
   "project": "Prometheus Hyperscale Casper",
   "source_mentions": 2,
   "locality": "Casper",
   "state": "Wyoming",
   "builder": "Prometheus Hyperscale",
   "customer": null,
   "capacity_gw": 1.5,
   "capacity_basis": "proposed",
   "status": "proposed",
   "target_date": "2028",
   "source_url": "https://newsweek.com/data-centers-proposed-largest-underground-water-reservoir-us-12118563",
   "latest_source_date": "2026-06-28T14:00:00"
  },
  {
   "project": "AWS Oregon: $12B 1GW Exascale AI Data Center Morrow County",
   "source_mentions": 2,
   "locality": "Boardman / Umatilla (Morrow County)",
   "state": "Oregon",
   "builder": "Amazon Web Services",
   "customer": null,
   "capacity_gw": 1.0,
   "capacity_basis": "Full Builtout",
   "status": "Under Construction (March 2026)",
   "target_date": "2032 (Pending Nuclear Timeline)",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Project Marvel - Bessemer Hyperscale",
   "source_mentions": 2,
   "locality": "Bessemer",
   "state": "AL",
   "builder": "Logistics Land Investments LLC",
   "customer": null,
   "capacity_gw": 1.2,
   "capacity_basis": "planned capacity",
   "status": "Planned",
   "target_date": null,
   "source_url": "https://datacentercompass.com/guides/list-of-us-data-centers-under-construction",
   "latest_source_date": "2026-04-19T00:00:00"
  },
  {
   "project": "IREN Sweetwater 1",
   "source_mentions": 2,
   "locality": "Sweetwater, TX (Nolan County)",
   "state": "TX",
   "builder": "IREN Limited",
   "customer": null,
   "capacity_gw": 1.4,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": "https://datacentercompass.com/guides/list-of-us-data-centers-under-construction",
   "latest_source_date": "2026-04-19T00:00:00"
  },
  {
   "project": "Stratos Project",
   "source_mentions": 2,
   "locality": "Box Elder County",
   "state": "Utah",
   "builder": "O'Leary Digital (MIDA)",
   "customer": null,
   "capacity_gw": 9.0,
   "capacity_basis": "announced load",
   "status": "proposed",
   "target_date": null,
   "source_url": "https://powertracker.io/rankings",
   "latest_source_date": "2026-05-18T23:52:00"
  },
  {
   "project": "Related Digital campus",
   "source_mentions": 2,
   "locality": "Saline Township",
   "state": "Michigan",
   "builder": "Related Digital",
   "customer": "OpenAI",
   "capacity_gw": 1.0,
   "capacity_basis": "project",
   "status": "planned",
   "target_date": null,
   "source_url": "https://datacenterdynamics.com/en/news?company=openai&term=colocation-wholesale",
   "latest_source_date": "2026-08-27T00:00:00"
  },
  {
   "project": "Project Artemis",
   "source_mentions": 2,
   "locality": "Abilene",
   "state": "Texas",
   "builder": "Lancium",
   "customer": "Microsoft",
   "capacity_gw": 2.0,
   "capacity_basis": "ultimate planned",
   "status": "in development",
   "target_date": "2025",
   "source_url": "https://datacenterdynamics.com/en/news/oracle-to-lease-texas-data-center-from-cryptomining-and-ai-firm-crusoe-report",
   "latest_source_date": "2026-08-11T00:00:00"
  },
  {
   "project": "AWS Project Starbound Mississippi: $13B 1GW+ AI Cluster",
   "source_mentions": 2,
   "locality": "Madison County (Canton/Ridgeland) & Vicksburg",
   "state": "Mississippi",
   "builder": "Amazon Web Services",
   "customer": null,
   "capacity_gw": 1.0,
   "capacity_basis": "Total Campus Goal",
   "status": "Under Construction / Initial Power-Up (March 2026)",
   "target_date": "March 2026",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Amazon Project Star: $11B Indiana Hyperscale AI Campus",
   "source_mentions": 2,
   "locality": "New Carlisle",
   "state": "Indiana",
   "builder": "Amazon Web Services",
   "customer": null,
   "capacity_gw": 1.0,
   "capacity_basis": "Full Builtout",
   "status": "Under Construction / Rapid Structural Build (May 2026)",
   "target_date": "Late 2026",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Fermi America Project Matador HyperGrid Campus",
   "source_mentions": 2,
   "locality": "Amarillo",
   "state": "TX",
   "builder": "Fermi America",
   "customer": "Fermi America (own AI campus)",
   "capacity_gw": 6.0,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Meta \"Project Seafox\"",
   "source_mentions": 2,
   "locality": "El Paso",
   "state": "Texas",
   "builder": "Meta",
   "customer": "Meta",
   "capacity_gw": 1.0,
   "capacity_basis": "ultimate announced data-center electrical load",
   "status": "under construction or in advanced planning",
   "target_date": null,
   "source_url": "https://datacenterdynamics.com/en/news/meta-files-to-expand-campus-in-el-paso-texas-with-12-new-buildings",
   "latest_source_date": "2026-08-05T00:00:00"
  },
  {
   "project": "Fermi America Data Center-Power Campus",
   "source_mentions": 2,
   "locality": null,
   "state": "Texas",
   "builder": "Fermi America",
   "customer": null,
   "capacity_gw": 11.0,
   "capacity_basis": "Installation Capacity",
   "status": "Announced",
   "target_date": null,
   "source_url": "https://enkiai.com/distributed-energy/oracle-natural-gas-2025-2300-mw-volta-grid-fleet",
   "latest_source_date": "2026-06-09T04:56:26"
  },
  {
   "project": "STAK Energy Campus (North Slope)",
   "source_mentions": 2,
   "locality": "Umiat Meridian",
   "state": "AK",
   "builder": "STAK Energy",
   "customer": null,
   "capacity_gw": 3.0,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "xAI Colossus 2",
   "source_mentions": 2,
   "locality": "Memphis",
   "state": "TN",
   "builder": "xAI",
   "customer": null,
   "capacity_gw": 1.5,
   "capacity_basis": null,
   "status": "operational",
   "target_date": null,
   "source_url": "https://siliconreport.com/ai-datacenter-power-crunch-electricity-bottleneck-31b33b49",
   "latest_source_date": "2026-07-03T02:44:03"
  },
  {
   "project": "Clean Campus",
   "source_mentions": 2,
   "locality": "Abilene",
   "state": "Texas",
   "builder": "Lancium",
   "customer": "Crusoe",
   "capacity_gw": 1.2,
   "capacity_basis": "announced project capacity",
   "status": "in development",
   "target_date": null,
   "source_url": "https://datacenterknowledge.com/data-center-construction/lancium-nvidia-partner-on-gigawatt-scale-ai-data-centers",
   "latest_source_date": "2026-08-25T12:33:39"
  },
  {
   "project": "Nebius Highridge",
   "source_mentions": 2,
   "locality": "Butler Township",
   "state": "Pennsylvania",
   "builder": "Nebius Group",
   "customer": null,
   "capacity_gw": 1.2,
   "capacity_basis": "Planning",
   "status": "Planning",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Goodnight",
   "source_mentions": 2,
   "locality": "Claude",
   "state": "TX",
   "builder": "Crusoe",
   "customer": null,
   "capacity_gw": 1.0,
   "capacity_basis": "hyperscale deployment",
   "status": "under construction",
   "target_date": null,
   "source_url": "https://aterio.io/blog/where-are-openai-s-five-new-hyperscale-campuses-being-built",
   "latest_source_date": "2025-09-24T18:20:00"
  },
  {
   "project": "Project Domino",
   "source_mentions": 2,
   "locality": "Lebanon",
   "state": "IN",
   "builder": "Meta",
   "customer": "Meta",
   "capacity_gw": 1.0,
   "capacity_basis": null,
   "status": "announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "EdgeCore Louisa County Campus",
   "source_mentions": 2,
   "locality": "Louisa County",
   "state": "VA",
   "builder": "EdgeCore Digital Infrastructure",
   "customer": null,
   "capacity_gw": 1.1,
   "capacity_basis": "announced capacity",
   "status": "Announced",
   "target_date": null,
   "source_url": "https://datacentercompass.com/guides/list-of-us-data-centers-under-construction",
   "latest_source_date": "2026-04-19T00:00:00"
  },
  {
   "project": "PowerHouse & Provident - Grand Prairie",
   "source_mentions": 2,
   "locality": "Grand Prairie",
   "state": "TX",
   "builder": "PowerHouse Data Centers / Provident",
   "customer": null,
   "capacity_gw": 1.8,
   "capacity_basis": "planned capacity",
   "status": "Under Construction",
   "target_date": null,
   "source_url": "https://datacentercompass.com/guides/list-of-us-data-centers-under-construction",
   "latest_source_date": "2026-04-19T00:00:00"
  },
  {
   "project": "Joliet Technology Center",
   "source_mentions": 2,
   "locality": "South Joliet",
   "state": "Illinois",
   "builder": "PowerHouse Data Centers and Hillwood",
   "customer": null,
   "capacity_gw": 1.2,
   "capacity_basis": "1,200 MW (1.2 GW)",
   "status": "Approved / Pre-Construction (March 19, 2026)",
   "target_date": "2030",
   "source_url": "https://cloudnews.tech/ai-transforms-america-into-a-giant-map-of-new-data-centers",
   "latest_source_date": "2026-05-12T12:05:10"
  },
  {
   "project": "Chevron Permian Basin Data Center Power Plant",
   "source_mentions": 2,
   "locality": "Permian Basin",
   "state": "TX",
   "builder": "Chevron Corp.",
   "customer": null,
   "capacity_gw": 2.5,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Tract data center campus with on-site generation",
   "source_mentions": 2,
   "locality": "New Braunfels",
   "state": "TX",
   "builder": "Tract",
   "customer": null,
   "capacity_gw": 2.0,
   "capacity_basis": "announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Nexus Hubbard Campus",
   "source_mentions": 2,
   "locality": "Hubbard",
   "state": "OH",
   "builder": "Nexus",
   "customer": "Nexus Data Centers",
   "capacity_gw": 7.2,
   "capacity_basis": "ultimate planned",
   "status": "under construction",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "OpenAI Stargate Wisconsin",
   "source_mentions": 2,
   "locality": null,
   "state": "WI",
   "builder": "Oracle",
   "customer": "OpenAI",
   "capacity_gw": 1.3,
   "capacity_basis": null,
   "status": "operational",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "TECfusions Keystone Connect",
   "source_mentions": 2,
   "locality": "Pennsylvania Coal Region",
   "state": "PA",
   "builder": "TECfusions",
   "customer": null,
   "capacity_gw": 3.0,
   "capacity_basis": "planned capacity",
   "status": "Under Construction",
   "target_date": null,
   "source_url": "https://datacentercompass.com/guides/list-of-us-data-centers-under-construction",
   "latest_source_date": "2026-04-19T00:00:00"
  },
  {
   "project": "Quantum Frederick Campus",
   "source_mentions": 2,
   "locality": "Frederick",
   "state": "MD",
   "builder": "TPG Real Estate / Quantum Loophole",
   "customer": null,
   "capacity_gw": 2.0,
   "capacity_basis": "planned capacity",
   "status": "Under Construction",
   "target_date": null,
   "source_url": "https://datacentercompass.com/guides/list-of-us-data-centers-under-construction",
   "latest_source_date": "2026-04-19T00:00:00"
  },
  {
   "project": "Crusoe and Lancium Announce 1.0 Gigawatt AI Data Center Campus in Childress, Texas",
   "source_mentions": 2,
   "locality": "Childress",
   "state": "Texas",
   "builder": "Lancium",
   "customer": "a leading hyperscale technology company",
   "capacity_gw": 1.0,
   "capacity_basis": "announced",
   "status": "announced",
   "target_date": "Q3 2026",
   "source_url": "https://finance.yahoo.com/technology/ai/articles/crusoe-lancium-announce-1-0-140000671.html",
   "latest_source_date": "2026-07-15T14:00:00"
  },
  {
   "project": "Fermi Project Matador",
   "source_mentions": 2,
   "locality": "Amarillo",
   "state": "Texas",
   "builder": "Fermi",
   "customer": null,
   "capacity_gw": 11.0,
   "capacity_basis": "campus",
   "status": "paused construction phase",
   "target_date": null,
   "source_url": "https://newsweek.com/data-centers-proposed-largest-underground-water-reservoir-us-12118563",
   "latest_source_date": "2026-06-28T14:00:00"
  },
  {
   "project": "Google Project Cannoli: $5B 1GW Michigan AI Data Center",
   "source_mentions": 2,
   "locality": "Van Buren Township",
   "state": "Michigan",
   "builder": "Panattoni",
   "customer": "Google",
   "capacity_gw": 1.0,
   "capacity_basis": "maximum load or contract capacity",
   "status": "proposed",
   "target_date": "December 2028",
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Richmond County AI Innovation Campus",
   "source_mentions": 2,
   "locality": "Richmond County",
   "state": "North Carolina",
   "builder": "AWS",
   "customer": null,
   "capacity_gw": 1.0,
   "capacity_basis": "full build-out",
   "status": "Under Construction",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "TeraWulf Morgantown data center hub",
   "source_mentions": 2,
   "locality": "Charles County (Morgantown)",
   "state": "MD",
   "builder": "TeraWulf",
   "customer": null,
   "capacity_gw": 1.0,
   "capacity_basis": "Announced",
   "status": "Announced",
   "target_date": null,
   "source_url": null,
   "latest_source_date": null
  },
  {
   "project": "Memphis AI data center campus",
   "source_mentions": 2,
   "locality": "Memphis",
   "state": "Tennessee",
   "builder": "xAI",
   "customer": "xAI",
   "capacity_gw": 2.0,
   "capacity_basis": "ultimate planned",
   "status": "growing",
   "target_date": null,
   "source_url": "https://thejobwalk.com/p/xai-files-659m-permit-for-new-building-at-memphis-ai-data-center-campus",
   "latest_source_date": "2026-03-06T11:09:34"
  },
  {
   "project": "River Bend",
   "source_mentions": 2,
   "locality": "West Feliciana Parish",
   "state": "Louisiana",
   "builder": "Hut 8",
   "customer": "Fluidstack",
   "capacity_gw": 1.0,
   "capacity_basis": "potential to scale by up to an additional 1,000 megawatts of utility capacity",
   "status": "first phase of construction is underway",
   "target_date": "second quarter of 2027",
   "source_url": "https://datacenterdynamics.com/en/news/hut-8-signs-245mw-capacity-deal-with-fluidstack-as-part-of-multi-gigawatt-partnership-with-anthropic",
   "latest_source_date": "2026-08-05T00:00:00"
  },
  {
   "project": "Crusoe Project Jade",
   "source_mentions": 2,
   "locality": "Laramie County",
   "state": "Wyoming",
   "builder": "Crusoe",
   "customer": null,
   "capacity_gw": 1.8,
   "capacity_basis": "announced",
   "status": "under construction",
   "target_date": "2027",
   "source_url": "https://newsweek.com/data-centers-proposed-largest-underground-water-reservoir-us-12118563",
   "latest_source_date": "2026-06-28T14:00:00"
  },
  {
   "project": "Sweetwater",
   "source_mentions": 2,
   "locality": "Nolan County",
   "state": "Texas",
   "builder": "IREN",
   "customer": null,
   "capacity_gw": 2.0,
   "capacity_basis": "announced load",
   "status": "building",
   "target_date": null,
   "source_url": "https://powertracker.io/rankings",
   "latest_source_date": "2026-05-18T23:52:00"
  }
 ],
 "notes": []
}